Public Accounts Committee's criticism of Libra has lessons for the NHS Spending watchdog slams magistrates IT project as one of worst PFI deals ever seen
- Posted:
- 17:05 07 Nov 2003
- Topics:
- Office Suites | Software Types | Network Infrastructure | Project Management | Software | Application Integration | IT Management | Software Development
As a minister, Geoff Hoon does not always have the Midas
touch.
He became deeply unpopular in Parliament when, as defence
secretary, he refused to order a new independent inquiry into the
crash of a Chinook helicopter on the Mull of Kintyre.
The crash was blamed on the pilots, but Computer Weekly and
others pointed out that faulty software might have been a
contributory factor.
Now Computer Weekly has learned that Hoon was the minister
responsible for approving Libra, an IT contract signed in 1998 that
was this week described by Edward Leigh, chairman of the House of
Commons Public Accounts Committee, as "one of the worst PFI deals
we have seen".
In a speech to the Nottinghamshire Branch of the Magistrates
Association on 15 October 1998 Hoon, a barrister, announced details
of Libra as an IT project for hundreds of magistrates courts that
would "not merely standardise existing systems or plug gaps in
them".
Hoon, the then Home Office minister, said, "The Libra system will
mean that a single supplier will take full responsibility for the
development of software, the supply of hardware and the work that
is necessary to ensure that systems are integrated."
Things did not work out as planned. A 10.5-year contract with
Fujitsu that was originally priced by the supplier at £146m
turned into an 8.5-year deal at a total cost to the Lord
Chancellor's Department of £390m, after the supplier found it
was unable to deliver core caseworking software to magistrates
courts.
Hoon's expectation of a single national supplier of Libra has also
evolved so there are now three suppliers, two of which have been
appointed this year, to do the work that was originally assigned to
one company, Fujitsu.
One of the three suppliers is STL, a long-established supplier to
magistrates courts. Under a contract awarded in January, it will
deliver the core national caseworking system that Fujitsu failed to
deliver.
The software will help to manage the scheduling of hearings, the
results of cases and produce all the case-related documents and the
enforcement process. Fujitsu is providing the hardware and
infrastructure; and Accenture is delivering the systems integration
for Libra.
Originally Fujitsu had been contracted to deliver all of these
elements of Libra.
The three contracts, together with the department's internal
expenses, bring the total cost of Libra to £390m.
This is £234m more than Fujitsu's first submitted tender
of £146m in May 1998, when the department's internal costs
were estimated at a further £10m.
Under Whitehall's original plans, magistrates courts were supposed
to have replaced their systems from different manufacturers with
standardised systems by 1993.
Today, 10 years later, after three failed projects with a variety
of suppliers, magistrates courts still do not have standardised
systems to handle cases.
Fujitsu had twice threatened to quit the Libra contract, first in
1999 and again in 2001, when it told the government that it
anticipated losses on the contract of £200m by 2013.
The Lord Chancellor's Department, anxious not to lose its main
supplier, which was part of the way through delivering networked
PCs to magistrates courts, signed a new contract to give Fujitsu
more money and absolve it of any responsibility to deliver the core
caseworking software.
Fujitsu is now simply delivering the infrastructure, which
comprises mainly networked PCs running Microsoft Office. Fujitsu is
being paid for its management and other costs, plus a profit and
contingency, but will bear none of the major PFI risks it accepted
in the original contract.
Fujitsu may get even more than the £232m it is due under the
revised Libra contract. The project's risks now lie almost entirely
with the taxpayer and a review of the project by a Gateway team
from the Office of Government Commerce in February 2002 concluded
that Fujitsu may seek additional money at every stage of the
integration of the core application (from STL) with the
infrastructure.
This week the Public Accounts Committee said in a detailed report
on Libra, "ICL [now renamed Fujitsu] did not take responsibility
for the risks transferred to it."
The committee concluded that that Fujitsu did not understand the
department's requirements, took on excessive risk in the original
contract and under-priced its bid. "It performed poorly throughout
and could not meet the target dates for delivery of the core
application," it said.
As a result of the failures of Fujitsu and the Lord Chancellor's
Department, the cost of the project "has more than doubled in just
four years to almost £400m and magistrates' courts still not
have the IT systems they need to manage their workload properly",
the report said.
But the committee's report into the affair, which was based on an
investigation by public spending watchdog the National Audit
Office, told only part of the story.
Despite a particularly tenacious inquiry by auditors and the
Public Accounts Committee, their otherwise penetrating reports do
not reveal the full evidence of the warnings that were ignored by
the Lord Chancellor's Department.
Nor do the reports fully detail Whitehall's dissemination of
misshapen official information about the project, or the
bureaucratic secrecy which turned many end-users in magistrates
courts into sceptics and even antagonists, even though their
co-operation was essential to the project's success.
The secrecy has continued. For several months this year, Richard
Bacon, a member of the Public Accounts Committee, has tried
exhaustively, with the full support of the all-party committee, to
establish from the Lord Chancellor's Department exactly what the
taxpayer is getting in return for the £232m that Fujitsu will
receive for delivering a new infrastructure for magistrates
courts.
Bacon said he has received much information from Fujitsu on the
breakdown of the £232m, but believed that he and the committee
have not got to the full truth. "I do not think we have had full
co-operation from Fujitsu or the department," said Bacon.
Dispelling the notion in Whitehall departments that the Public
Accounts Committee can find out anything it wants, the committee's
report on Libra said.
"The department used independent consultants [Gartner] to
benchmark the price, which was not tested in competition and
appears very expensive for what is being provided. The department
was nevertheless unable to say how ICL's price for the
infrastructure element of the Libra project was constructed."
Fujitsu had provided a note to MPs which gave a breakdown of the
£232m costs, but the committee's report said, "This evidence
was unconvincing in demonstrating that £232m was not an
excessive price to pay for just the infrastructure element
project.
"We remain unconvinced that £232m was a fair price to
pay."
With truly British understatement the committee's report concluded,
"More thorough analysis is needed before departments agree to pay
more than twice the tender price."
The lack of accountability in the higher echelons of Whitehall and
the ability of mandarins to take risks and spend money without fear
of personal consequences, sets the public sector apart from the
private sector.
When, for example, a major internet-based project at Prudential
Europe collapsed in 2001, an entire layer of senior executives lost
their jobs and had to leave the building within minutes of being
told.
On the Libra project, the accounts committee's report pointed out
that nobody in the public sector has been held accountable for the
disaster. "As a result of the failures on the project, some people
[at Fujitsu] had their contracts terminated and ICL had bought in
new management," the report said.
In contrast, the report also noted that the department
transferred staff elsewhere but "no one lost their job".
The report added, "The department believed that people who had made
decisions made on the best advice available at the time should not
have their careers blighted for having done what seemed to be their
duty".
Yet blame for the debacle does not appear to lie with civil
servants at the coalface. The National Audit Office reported that
within the Lord Chancellor's Department many people regarded the
Libra contract as "unworkable" and the Fujitsu team saw it as
"something it [Fujitsu] should never have signed up to".
However, the lack of accountability of mandarins, contrasted with
the fear of job losses in the private sector, could help explain
why victims of IT disasters in the private sector, such as
Prudential Europe, take radical steps to pre-empt the collapse of
subsequent projects, but government departments, including the
Department of Health and the Home Office, have repeated
failures.
Compounding this lack of accountability is the unending struggle of
MPs, as scrutineers of IT projects, to obtain accurate information
about difficulties on important schemes. This week's report of the
Public Accounts Committee's has a section on what it terms the
"accuracy of evidence" it received.
At a hearing of the accounts committee on 24 June 2002, MPs asked
the department's accounting officer whether it was true that the
department was not proceeding with that part of the Libra contract
which would provide the software for court business.
The official replied, "No that is not my understanding. My
understanding is that we are in negotiation with the company ICL,
now called Fujitsu Services, about the timescale of the cost of the
software package because of the delay, and we intend to bring that
to a conclusion just as soon as we can so we know where we
are."
However, the department had decided in February 2002 that ICL
should not continue with the development of the core software
application. ICL itself had learned of this decision made by the
department in March 2002.
Explaining the contradiction later, the official told the Public
Accounts Committee that he had been trying to protect the
commercial negotiation that was still in train. At the time of the
hearing in June 2002, the deal with Fujitsu had not been
finalised.
"The accounting officer accepted that he could have handled the
situation differently by, for example, presenting the information
to the committee in confidence," said the Public Accounts
Committee's report. It added that the accounting officer "regretted
giving incorrect information and stressed that he had not
deliberately sought to mislead the committee".
But there have been other departmental or ministerial statements to
Parliament which have lacked candidness. In July 2000, Jane
Kennedy, the then parliamentary secretary at the Lord Chancellor's
Department, was asked by Alan Williams of the Public Accounts
Committee about the value of PFI contracts managed by her
department.
She gave the cost of Libra as £75m instead of actual costs,
which by then had risen from £184m to £319m. It is now
known that Kennedy's figure was low because it quoted only the
capital and not the revenue sums allocated to the project.
Kennedy also replied "no" when asked whether the contract had been
the subject of refinancing. In fact, the cost of Libra had been
revised two months earlier, in May 2000, according to a report by
the National Audit Office.
In May 2000, the Lord Chancellor's department signed a revised
contract for the delivery of Libra. "The value of the contract
increased from £184 to £319m," said the National Audit
Office.
Magistrates court staff have written to Computer Weekly about their
difficulties in obtaining accurate information about Libra. The
tenor of the correspondence suggested that secrecy has contributed
to the profound disillusionment of end-users.
"The Lord Chancellor's Department has attempted to counter
hostility [among end-users] with a series of upbeat seminars and
frequent visits to key individuals to give assurances," said one
letter.
Another letter, written in 2001, accused the department of being
economical with the truth in its rebuttals of an article in
Computer Weekly.
There are remarkable parallels between the problems of secrecy and
lack of consultation causing disaffection and scepticism among
Libra's end-users, and the criticisms of the Department of Health
as it approaches the signing of IT contracts with local service
providers, worth potentially billions of pounds.
But if senior mandarins cannot be held accountable for their
decisions, in part because MPs do not have the full facts with
which to challenge statements they are given, one wonders whether
IT disasters in the public sector such as Libra will ever
cease.