In this blog entry the two leaders of the £5bn Defence Information Infrastructure contract [DII], who represent the Ministry of Defence and the Atlas consortium of suppliers, led by services company EDS, answer our questions about progress and challenges, and the lessons learned.
Their defence of the DII follows a joint investigation of the DII by Computer Weekly and Channel 4 News. Bob Quick, the MoD's programme director for the scheme, and Howard Hughes, Chief Operating Officer of a consortium of suppliers, Atlas, did not deny there have been problems but said the scheme was on a sound footing.
**
Why was there a need to change the DII contract in December 2006? [The Atlas consortium was awarded a DII add-on contract, increment 2a, worth an extra £750m, in December 2006. The first increment was worth £2.3bn to Atlas. Under increment 1 about 70,000 systems should have been delivered by mid-2007. Today only about 16,000 terminals have been delivered.]
Bob Quick said:
“The contract wasn’t changed. We did add at the end of 2006 another increment. It’s an incremental contract to de-risk the delivery. At the end of 2006 increment 2a was added which is a further set of UADs [user access devices such as desktop systems and laptops]. The programme has had some challenges as we have rolled forward.
“As of today we [have] in the order of 16,000 UADs and about 56,000 account holders. The early part of the programme very much concentrated on the delivery to the users who had some of those older systems because we needed to get the infrastructure out there to support the HR applications, both civilian and military, and some of the other defence change applications coming through.
“So we certainly were not rolling out the volume of UADs that we anticipated at the time of contract award. But we have now done about 400 of the 600 sites in increment 1 so [we're] about two thirds of the way through in terms of sites. The number of terminals we are now rolling out has ramped up over the last few months and we are regularly rolling out 3,000 and 4 ,000 a month which will assist in getting the programme back to the combined plan for [increments] 1a and 2.”